2024-2025 Audit Report: Sports: Rs 172 Million for an Abandoned Project
One of the most striking cases concerns the Triolet multi-sports complex project. Initially estimated at Rs 172.4 million, this project was abandoned after preliminary work. Following a Supreme Court decision, the state had to pay a total compensation of Rs 19.34 million to the contractor, highlighting poor planning and avoidable costs. Additionally, a settlement in another dispute cost Rs 39.35 million, escalating the financial impact.