Question Time | Renewable Energies: Corexsolar/CEB Contracts Facing Termination
The promoter still does not have the necessary Environmental Impact Assessment (EIA), Land Control Permit (LCP), Building and Land Use Permit (BLUP), nor Wayleaves for the land access related to these two projects. The Minister of Energy, Patrick Assirvaden, confirmed in response to a question from Joanna Bérenger that the contracts between the Central Electricity Board (CEB) and Corexsolar International (Mauritius) Ltd are in the process of being terminated.